- Connecting Bridge can be drafted within the Plot connecting two Proposed Works or within a Floor Plan.
- Connecting Bridge at Plot level must be drafted such that it connects the two Proposed Works.
- In case of connecting bridge at Floor Plan level:
- must be drafted outside the Built Up Area outline of the Floor Plan
- must have at least one segment exactly coinciding with the Built Up Area outline polyline of the Floor Plan.
- Building Permission
- Layout With Housing And Gated Community & Layout With Housing Without Gated Community